Visitors watch a dredging crew pump out sand from John's Pass Village & Boardwalk on March 25 in Madeira Beach.

Visitors watch a dredging crew pump out sand from John's Pass Village & Boardwalk on March 25 in Madeira Beach.

Before-and-after photos of John’s Pass dredging project. It’s now complete

Before-and-after photos show the area where over 13,000 cubic yards of sand was removed.

By Jefferee Woo

Thirty years after it was first identified as a problem, the long-awaited dredging of John’s Pass is finally complete.

Bayside Dredging, the company contracted for the project, removed more than 13,000 cubic yards of sand from the pass, helping to restore safer navigation through one of Pinellas County’s busiest waterways. The dredged material was hauled about 1.5 miles to a city-owned property at 555 150th Ave., where it will be stockpiled for future use as fill material.

A fisherman casts while dredging begins in March along John's Pass.
A fisherman casts while dredging begins in March along John's Pass. [ JEFFEREE WOO | Times ]
Bayside Dredging checks the depth while surveying near the John's Pass Bridge.
Bayside Dredging checks the depth while surveying near the John's Pass Bridge. [ JEFFEREE WOO | Times ]

At an average of 15 cubic yards per truckload, the operation required roughly 870 trips between the pass and the storage site. Work began Feb. 9 and wrapped up May 28.

A section of a public parking lot served as the project’s staging area, while the remainder of the lot stayed open to beachgoers and visitors throughout construction.

Dangerous currents have plagued the John's Pass area for decades due to sand building along the pass.
Dangerous currents have plagued the John's Pass area for decades due to sand building along the pass. [ JEFFEREE WOO | Times ]
Shoppers spend time at the John's Pass Village & Boardwalk which is near the area where dredging took place in Madeira Beach.
Shoppers spend time at the John's Pass Village & Boardwalk which is near the area where dredging took place in Madeira Beach. [ JEFFEREE WOO | Times ]

“Our method was not only efficient, but it allowed the parking lot to stay open, which allowed the public to use the beach and kept the small businesses on the boardwalk generating revenue,” said John Schamp, vice president of Bayside Dredging.

The buildup of sand in the pass had long been considered a public safety concern because of strong currents and restricted navigation. With the channel restored, boaters will have improved access to local marinas, while the dredging is also expected to benefit the surrounding marine ecosystem.

Sand is pumped through pipes and into a large container. The sand ended up in dump trucks, then was hauled away.
Sand is pumped through pipes and into a large container. The sand ended up in dump trucks, then was hauled away. [ JEFFEREE WOO | Times ]
Crew members from Bayside Dredging watch as sand is transferred to a dump truck.
Crew members from Bayside Dredging watch as sand is transferred to a dump truck. [ JEFFEREE WOO | Times ]

“The project went exceptionally well and exactly as planned,” Schamp said. “The only hurdle we had to battle was getting the dredge flow rate dialed in at the beginning and dealing with the ripping current.”

A dredging machine is close to the boardwalk in March.
A dredging machine is close to the boardwalk in March. [ JEFFEREE WOO | Times ]
Bayside Dredging checks the depth of the water near John's Pass in February.
Bayside Dredging checks the depth of the water near John's Pass in February. [ JEFFEREE WOO | Times ]
John's Pass visitors walk past the area being dredged.
John's Pass visitors walk past the area being dredged. [ JEFFEREE WOO | Times ]
An excavator scoops out sand from the water.
An excavator scoops out sand from the water. [ JEFFEREE WOO | Times ]
Pipes are floated along the water to transport dredged sand.
Pipes are floated along the water to transport dredged sand. [ JEFFEREE WOO | Times ]
Dredging continued in April along John's Pass.
Dredging continued in April along John's Pass. [ JEFFEREE WOO | Times ]
Over 13,000 cubic feet of sand was removed and stored near John's Pass.
Over 13,000 cubic feet of sand was removed and stored near John's Pass. [ JEFFEREE WOO | Times ]
A boom arm controls a pipe used to suck sand from the bottom.
A boom arm controls a pipe used to suck sand from the bottom. [ JEFFEREE WOO | Times ]
The John's Pass Village & Boardwalk after the completion of the dredging project on June 3.
The John's Pass Village & Boardwalk after the completion of the dredging project on June 3. [ JEFFEREE WOO | Times ]
Sand was cleared from underneath the John's Pass Bridge making navigation much easier.
Sand was cleared from underneath the John's Pass Bridge making navigation much easier. [ JEFFEREE WOO | Times ]
The John's Pass Village & Boardwalk is seen after more than 13,000 cubic yards of sand was removed.
The John's Pass Village & Boardwalk is seen after more than 13,000 cubic yards of sand was removed. [ JEFFEREE WOO | Times ]
Author
Author
Jefferee Woo
Advertisement

Most Popular

Event Calendar

Advertisement

Newsletters

Advertisement